...construction contracts: PRICE ADJUSTMENT FOR SUSPENSION, DELAYS, OR INTERRUPTION OF WORK (NOVEMBER 1961) (a) The Contracting Officer may order the Contractor...interrupted by an act of the Contracting Officer in the §7.603 administration oí the contract, or by his failure to act within the time specified in the... | |
| 1977 - 1240 páginas
...period of time as he may determine to be appropriate for the convenience of the Government. (b) If the performance of all or any part of the work Is,...of the Contracting Officer In the administration of this contract, or by his failure to act within the time specified in this contract (or If no time is... | |
| 1982 - 536 páginas
...period of time as he may determine to be appropriate for the convenience of the Government. (b) If the performance of all or any part of the work is,...of the Contracting Officer in the administration of this contract, or by his failure to act within the time specified in this contract for if no time is... | |
| 1993 - 1178 páginas
...such period of time as he may determine to be appropriate for the convenience of the owner. (b) If the performance of all or any part of the work is,...suspended, delayed, or interrupted by an act of the owner in administration of this contract, or by his failure to act within the time specfled in this... | |
| 1983 - 788 páginas
...such period of time as he may determine to be appropriate for the convenience of the owner. (b) If the performance of all or any part of the work Is,...suspended, delayed, or interrupted by an act of the owner In administration of this contract, or by his failure to act within the time specfled In this... | |
| 1994 - 1186 páginas
...such period of time as he may determine to be appropriate for the convenience of the owner. (b) If the performance of all or any part of the work is,...suspended, delayed, or interrupted by an act of the owner in administration of this contract, or by his failure to act within the time specfled in this... | |
| 1974 - 788 páginas
...determine to be appropriate for the convenience of the Government. (Ы If the performance of all or any pan of the work is. for an unreasonable period of time,...of the Contracting Officer in the administration of this contract, or by his failure to act within the time specified in this contract (or if no time is... | |
| 1971 - 664 páginas
...period of time as he may determine to be appropriate for the convenience of the Government. (b) If the performance of all or any part of the work is,...time, suspended, delayed, or interrupted by an act oí the Contracting Officer in the administration of this contract, or by his failure to act within... | |
| 1988 - 632 páginas
...time that the Contracting Officer determines appropriate for the convenience of the Government. (b) If the performance of all or any part of the work is,...period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting... | |
| 2001 - 652 páginas
...time that the Contracting Officer determines appropriate for the convenience of the Government. (b) If the performance of all or any part of the work is,...period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting... | |
| |